Energinet consults on adapting Denmark’s gas grid to surplus biomethane
Energinet’s draft methane plan confirms five reverse-flow plants by 2029 and lists one more, in North Jutland, for 2030. South Jutland and South Zealand get no listed fix, while oxygen and trace-substance limits may tighten as reverse-flow costs rise about sixfold by 2040. Responses are due 4 December 2026.
Just over 8 TWh of biomethane covered about 40% of Danish gas use in 2025. Only about 15%, 1.3 TWh, reached transmission; reverse flow alone carried about 12%. The rest was used near where it was made.
Energinet expects 50–60% of production to enter transmission by 2050, about 9 TWh. That is a tenfold rise, and it leaves out plants that may connect directly to transmission.
These forecasts rest on the Danish Energy Agency’s 2025 analysis assumptions (AF25), corrected by Energinet and Evida with market data. On that basis biomethane overtakes Danish gas demand in 2031–2032, after the 2030 political target, and exceeds 200% of demand in the long term.
Local surplus is already visible. In 2025 biomethane reached 153% of consumption in the southernmost Jutland distribution area, against 0.5% around Copenhagen. Demand differs too: households were about 60% of consumption east of the Great Belt in 2025, while business made up about 60% to the west.
Where the growth is expected
Zealand’s expected output roughly triples, and its full pipeline is about eight times today’s. Across Denmark, the full list (≈ 24 TWh) is nearly double expected output (≈ 13 TWh). Energinet treats that gap as possible upside, not as a planning case.
Energinet judges the five plants under construction sufficient for 2030, but with thin redundancy. Beyond them it lists one new plant and describes three gaps without listing a fix.
The five plants come from Energinet and Evida’s 2022 holistic plan, under which Evida links its grid into seven regional networks. Reverse-flow plants at Terkelsbøl, Højby and Viborg (2022) and a temporary plant at Karup (2023) already operate.
Biomethane projects on the list
The list’s “in maturation” stage is empty. North Jutland is the only possible project Energinet expects to take to approval soon.
Redundancy is the weak point to 2030
Region by region
No surplus near term: a large industrial user switching from coal absorbs it, and some gas moves south. If that user deviates, large surpluses can appear at short notice from 2027–2028. Seasonal surplus follows from the mid-2030s even if it does not.
Reverse-flow plant, possible project for 2030
The existing plant suffices in 2030 but is outgrown during the 2030s, and it cannot be expanded. A new plant from the 2022 plan was cancelled, with its approval, because the need was uncertain.
None listed; need “followed continuously”
Growth is higher than expected. Summer surplus must pass a distribution bottleneck already largely taken by existing and under-construction plants. More connections risk a “biomethane pocket” where gas is lost.
A new M/R station and distribution link around the bottleneck, and/or a line compressor in Evida’s grid; choice open. Not on Energinet’s list
Several areas exceed existing and planned capacity, but the need is very uncertain.
No initiatives yet; possible expansion of the planned plants
Energinet names two alternatives to new plants. It can lower pressure in dead-end transmission branches so distribution gas flows through them, or connect large plants directly to transmission.
Biomethane carries oxygen, hydrogen, sulphur compounds, ammonia and terpenes that fossil gas does not. Energinet manages this today by blending with oxygen-free Norwegian and North Sea gas. It says blending alone will not cope as volumes in transmission grow.
Oxygen: the Danish limit is 500 times Germany’s
The level injected biomethane may carry; depends on the upgrading technology
Met today by sending oxygen-free North Sea gas through a dedicated pipe
Risk of oxygen-rich “bubbles” rises markedly within five years
The Swedish operator Nordion has relaxed its limit broadly to Danish levels
Rising oxygen in injected gas to be assessed
Two developments tighten this. The hydrogen backbone converts one of the two parallel pipes to Germany, finishing in the second half of 2030. That ends the oxygen-free export route, and southern Jutland biomethane averages 0.1–0.2 mol% oxygen; Energinet says even blending cannot meet Germany’s limit.
For Poland, the risk is a “plug”: when flow stops and restarts, an unblended biomethane bubble reaches the border. Large new plants on Zealand raise that risk most, especially if connected directly to transmission, where many plants no longer average each other out.
Energinet sets out three options:
- 1Ask neighbours to adapt their limits, nationally or in a “biomethane zone”.
- 2Tighten the Danish oxygen limit to match export markets.
- 3Build oxygen-removal plants. The 2050 map marks possible oxygen-removal points; none is on the project list.
Hydrogen: a 0.05 mol% limit producers struggle to meet
Since 2024 Energinet applies a hydrogen limit of 0.05 mol% in transmission, with time-limited exceptions. Producers find it hard to meet, especially at start-up and with some feedstocks. Energinet cannot yet measure hydrogen in transmission, so it cannot relax the limit without affecting settlement.
E-methane adds hydrogen slip, mainly at start and stop. The development plan says Poland and Sweden do not accept hydrogen while Germany allows up to 2%; the needs analysis says neighbours do not regulate it explicitly. Under the EU gas package, a TSO must in principle accept up to 2 mol% if a neighbouring TSO asks, which would mean hydrogen metering at several stations and, at worst, hydrogen removal.
Sulphur and terpenes: the costliest trace substances
Trace substances cut deodorisation-filter performance to about a third of design, so filters are replaced far more often. Terpenes, typical of plant and food-waste feedstocks, mask the odorant and form black dust in compressors.
The revised gas-quality standard EN 16726:2025 tightens limits on sulphur compounds, and Energinet notes Danish rules may follow. Its listed responses include better metering, trace-removal plants, new filter materials and “possibly tightened requirements” on biomethane’s trace content.
Energinet expects the yearly cost of running reverse flow to rise from about DKK 38 million to about DKK 240 million towards 2040. Removing odorant drives most of the increase.
The 2040 deodorisation estimate is almost double the 2023 needs analysis. Trace substances, not the odorant itself, cause up to two-thirds of deodorisation cost. Energinet has tested a filter material that could cut costs substantially, and is weighing running more of the system odorised, as France does in transmission and storage.
Other cost lines
About DKK 40 million a year for ten years, mostly sea-pipeline inspection and three to four M/R stations a year. Biomethane connections take a rising share, as they wear faster than expected.
About DKK 10 million a year for measures under EU Regulation 2024/1787, plus leak detection and repair outside stations. Energinet holds its own target of a 10% cut on 2019 by 2030, although six new compressor stations come with the biogas programme.
About DKK 2 billion for physical security and monitoring under the Act on Strengthened Preparedness. The plan does not say how much falls on gas.
Once biomethane exceeds Danish demand, surplus must be exported, stored or absorbed by new users. The draft weakens the first and is cautious on the third.
Germany is converting the pipes that link it to Denmark to hydrogen, which sharply cuts border capacity both ways. Energinet states that exporting the volumes AF25 assumes is physically impossible. AF26 has since lowered assumed exports to Germany for the same reason.
Baltic Pipe transit dilutes biomethane, but oxygen bubbles are the risk (see gas quality).
Two Danish storage sites take surplus for winter; rising oxygen in the gas they receive needs assessment.
New large consumers
In single cases, ≈ 1.4 GW and a tenth of Baltic Pipe’s transit capacity. Highly uncertain; could need pipe duplication or a new compressor station, depending on location.
PtX plants (gas as feedstock)Very uncertain; may need larger M/R stations.
District-heating peak plantsTypically a bridge until the power grid is reinforced; no change to transmission expected.
All seek high capacity with an uncertain, possibly low, actual use. Data centres would burn gas when power prices are high. Energinet expects more interest because data centres sit in category four of the electricity connection queue. Gas users still connect at distribution level by default.
E-methane: the upside not in the forecast
E-methane combines surplus CO₂ from biogas plants with electrolytic hydrogen. It can lift green-gas output from the same biomass by 50–70%. Denmark has one plant today; many biogas plants sit near the planned hydrogen backbone, which could steady production and lower hydrogen slip. Energinet warns rapid growth could create surplus needing new initiatives.
New reverse-flow capacity still needs a final plan, an approval and a build. The one new plant, in North Jutland, would reach service in 2030 at the earliest.
The rules tighten for the next cycle
A draft executive order implementing Article 55 of the Gas Directive was consulted from 1 July to 28 August 2026. Entry into force is planned for 1 January 2027 (Høringsportalen).
As drafted, the ten-year view must list infrastructure for reverse flows and for decommissioning, each with a timeframe (§ 17). The Danish Utility Regulator would approve that view and could require changes to the methane part (§ 22). The order now in force governs this consultation.
All sources are first-party: Energinet, Evida, the Danish Energy Agency, Danish legislation and EU law. Values marked ≈ are read from charts in Energinet’s documents.