Nefco’s €6 million Vegger loan and Denmark’s biogas financing routes

Nefco announced the agreement on 19 October 2026. The disclosed structure combines lending through Fremsyn’s group with other financing and existing Danish Energy Agency support.[1]

Biogas production
Approx. 37 → up to 52
37 → 52
Swiss customer agreement
From late 2027, with GoOs
48
0204060 GWh
Current / contracted Production uplift, +15 GWh
19 OCT 2026
Agreement announced by Nefco.
LATE 2027
Swiss supplies reach 48 GWh annually.
2028
Full project completion expected.
ELEMENT · CONFIRMED POSITION
INSTRUMENT

€6 million loan.

BORROWER

Biogem A/S, Fremsyn’s trading subsidiary; funds are channelled through the group.

INVESTMENT

Acquisition and modernisation of Vegger, including upgrading, grid connection, CO₂ capture and hydrogen-based methanation.

OTHER FUNDING

Other financiers participate; the Danish Energy Agency supports an electrolysis-integration component, for demonstrating electrolysis integration.

PRODUCTION TARGET

Annual biogas production rises from approximately 37 GWh to as much as 52 GWh.

CO₂ CAPTURE

Capacity of up to 5,000 tonnes annually.

COMMERCIAL OUTLET

Long-term Swiss customer agreement, with Guarantees of Origin and volumes reaching 48 GWh annually from late 2027.

COMPLETION

Full completion expected in 2028.[1]

EIFO provides the closest domestic equivalent to Nefco’s financing. NIB and Nefco are Nordic institutions accessible to Danish borrowers; they are not Danish national subsidy programmes.

02.1 · LOANS Fund commercially assessed assets. EIFO · NIB · NEFCO → 02.2 · GRANTS Fund specified innovation, infrastructure or environmental activities. EUDP · GUDP · MUDP · JTF · IFD → 02.3 · OPERATING SUPPORT Depends on a separate entitlement. LEGACY RIGHTS · TENDERS →
02.1 — Commercial loans

Commercial loans: creditworthiness and co-financing determine access

MATURITY, YEARS · FINANCING SHARE
EIFO green loans
60% across portfolio
Up to 30
EIFO Vækstlån
50% of financing need
Up to 10 · 2-year grace
NIB
Up to 50% of costs
Normally 5–30
Nefco green loans
Share not published
Tenor negotiated individually
0102030 yrs
LOAN SIZE, € MILLION
NIB direct loans
Normally from €10m →
Nefco, advertised
€2–10m
Nefco, typical
€2–5m, larger possible
Vegger loan
€6m
05101520

EIFO amounts are DKK-denominated: Vækstlån from DKK200,000 with no published maximum; green loans carry no fixed project-level ceiling.

FINANCING ROUTE FOCUS AND ELIGIBILITY SIZE, STRUCTURE AND PRINCIPAL CONDITIONS

EIFO green loans and guarantees

Renewable-energy facilities, energy efficiency and resource efficiency. Eligible borrowers include private companies and qualifying public entities able to borrow commercially. EIFO assesses commercial viability and environmental contribution.

DKK8 billion overall mandate, continuing the former Danish Green Investment Fund’s activities. Senior or subordinated loans and guarantees, secured or unsecured, on market terms; maturity up to 30 years. The 60% financing ceiling applies across the portfolio, not as an entitlement for each project. The current regulation contains no fixed project-level amount ceiling.[2]

EIFO growth loans — Vækstlån

Companies needing investment capital beyond available bank financing. Positive equity and creditworthiness required. Normally a maximum of 499 employees, with financial-size thresholds and specific innovation exceptions.

DKK200,000 upwards, without a published maximum; EIFO’s contribution is 50% of the total financing need. Up to 10 years, with an initial two-year repayment grace period. CIBOR-linked, individually risk-priced lending; security and intercreditor arrangements are assessed case by case.[3]

Nordic Investment Bank — NIB

Larger investments with environmental or productivity benefits. Public and private borrowers; assessment covers credit quality, sustainability and project execution. Relevant to construction, expansion and associated CO₂ infrastructure.

Direct loans normally start at €10 million, generally cover up to 50% of project costs, and normally run for 5–30 years. Market-based pricing; structured, limited-recourse and non-recourse financing can be available. An InvestEU guarantee supports eligible lending but is not an additional cash grant.[4]

Nefco green loans

Nordic SMEs with an established commercial record and proven technology, generally TRL 8–9. Projects within the Nordics need strong demonstration value and international scaling potential.

Detailed guidance describes €2–5 million as typical, with larger amounts possible; its financing overview advertises €2–10 million. Pricing, security, tenor and repayment are negotiated individually. The borrower must demonstrate financial viability and measurable environmental benefits.[5]

02.2 — Grants

Grants: support attaches to eligible activities within the project

PROGRAMME POOL
Danish JTF
2025 call, closed
Up to 250 · North and South Jutland
EUDP
2026 round II
240 · shared with Green Labs DK and IEA
MUDP
2026 projects
130 · all environmental themes
0125250
PER-PROJECT AWARD RANGE
Danish JTF
Support up to 80%
Normally 5–40
GUDP
Up to five years
0.25–15
Innoexplorer
Innovation Fund Denmark
0.5–1.5
010203040

EUDP and MUDP co-finance defined activities without a published per-project range.

SCHEME FOCUS AND ELIGIBILITY RELEVANT TO BIOGAS FUNDING SCALE AND CONDITIONS

EUDP — Energy Technology Development and Demonstration Programme

Development and demonstration of innovative energy technologies, including methanation, feedstock conversion and integration with other energy processes. Danish CVR-registered companies, research institutions and qualifying public bodies can apply; foreign partners may participate under a Danish lead. Commercialisation and scalability must be demonstrated.

Competitive co-financing of defined development activities, with own financing demonstrated. The 2026 second-round pool was DKK240 million, shared with Green Labs DK and IEA activities — not reserved for biogas. Its September deadline had passed; decisions were expected in December 2026.[6]

GUDP — Green Development and Demonstration Programme

Innovation serving agriculture and the food-sector value chain. Relevant activities include agricultural feedstocks, digestion optimisation, nutrient recovery and digestate management. Projects must combine environmental benefits with commercial potential.

Development and demonstration grants of DKK250,000–15 million, for projects lasting up to five years. Funding rates depend on participant size, activity and applicable state-aid rules. It is not a general construction subsidy for energy plants.[7]

MUDP — Environmental Technology Development and Demonstration Programme

Development, testing and demonstration addressing environmental problems. Relevant applications include methane-loss reduction, wastewater digestion, ammonia recovery and resource efficiency.

DKK130 million available for projects in 2026 across environmental themes. Separate routes cover feasibility, verification, development and flagship demonstrations. Awards finance the environmental-technology project; they do not automatically cover the host plant’s wider investment.[8]

Danish Just Transition Fund — Fonden for Retfærdig Omstilling

CCUS, Power-to-X and pyrolysis development, investment and skills activities benefiting North and South Jutland. Companies of different sizes and public/research partnerships may qualify.

The 2025 call offered up to DKK250 million, normally DKK5–40 million per application, with support up to 80%, subject to state-aid limits. It closed on 10 October 2025, followed by awards in January 2026. This is geographically restricted, call-based finance.[9]

Innovation Fund Denmark

Earlier-stage research commercialisation, entrepreneurship and business–university research. Relevant routes include Innoexplorer, Innofounder and Industrial Researcher.

Innoexplorer provides DKK0.5–1.5 million to mature research-based business ideas from public institutions. Other programmes have distinct applicant and co-financing requirements. Recent methane-related awards include founder support and an industrial PhD; these finance technology and business development rather than commercial plant construction.[10]

Danish projects can also compete for the EU Innovation Fund, which is separate from Innovation Fund Denmark.
02.3 — Production support

Production support: existing rights remain distinct from new investment finance

Legacy biogas support CLOSED ~2020

Denmark’s legacy biogas support schemes closed to new entry around 2020, with connection and application deadlines governing eligibility. Existing support rights and production limits remain relevant to incumbent plants, including some conversions from combined heat and power to upgrading. A loan or investment grant does not itself confer those operating-support rights.[11]

Competitive green-gas tenders OUTSTANDING

The proposed competitive support tenders for biogas and other green gases remain outstanding. Their assumed production contribution from 2027 is not evidence of an opened tender or awarded support.[12]

The transactions below finance different uses of capital. Tønder and Sindal receive plant-specific loans; BioCirc’s equity strengthens group financing; Bigadan’s transaction finances an ownership acquisition. Vinkel’s facility also covers solar investment, while BioCirc’s NIB loan finances CO₂ infrastructure.

≈ converted at the DKK/€ rate implied by the source’s paired figures
{{ r.name }}
{{ r.date }} · {{ r.kind }}
{{ r.label }}
PROJECT AND FINANCING DATE SPONSOR / RECIPIENT AND FUNDED ACTIVITY AMOUNT AND PROVIDER TERMS AND STRUCTURE

Tønder Biogas

Signed 20 December 2024; announced February 2025

Tønder Biogas A/S; CIP Advanced Bioenergy Fund I. Construction and operation of a gas-to-grid plant exceeding 41 million Nm³ methane annually.

DKK250 million / €33.5 million — NIB

16-year loan. Dedicated plant financing; rate and security undisclosed.[13]

BioCirc group investment programme

Spring 2025

BioCirc Group Holding. Capital supporting group development, including Vinkel expansion, solar integration and CO₂ infrastructure.

DKK331.895 million — existing shareholders

Two equity capital increases. Group-level capital, without a published allocation to each asset; the final amount exceeds the initial DKK300 million announcement.[14]

Vinkel Biogas expansion and Vinkel Solar Park

June 2025

BioCirc. Joint financing of biogas expansion and the associated solar investment.

DKK250 million — external financier(s), unnamed

Project debt. The disclosed amount cannot be allocated entirely to biogas. Tenor, pricing and security undisclosed.[14]

BioCirc five-plant CO₂ programme

Signed 7 July 2025

BioCirc Group. CO₂ purification, liquefaction and transport infrastructure associated with five Danish biogas plants, enabling permanent geological storage.

DKK205 million / €27.5 million — NIB

Nine-year loan, supported by InvestEU. Finances carbon-removal infrastructure; it should not be reported as additional biomethane-production capacity.[15]

North Sky / Danish biogas expansion

Partnership announced April; JV confirmed June 2025

Skovgaard Energy and Sumitomo. Expansion of Danish biogas operations and development of an integrated biogas/e-SAF business.

Undisclosed — Sumitomo and Skovgaard Energy

Joint-venture equity participation. No public plant-by-plant capital allocation or confirmation of financing for the entire future e-SAF development.[16]

Bigadan platform investment

Announced 22 October 2025

Arjun Infrastructure Partners, through Infrastructure Alliance Europe 3. Increased ownership of Bigadan’s Danish biogas platform.

Equity consideration undisclosed; €67 million acquisition financing confirmed by lender’s counsel

Corporate acquisition finance. Lender and debt terms undisclosed. Bigadan’s planned CHP-to-grid conversions and CCUS expansion are not separately quantified within this transaction.[17]

Green2x Møn pilot

November 2025 investment agreement

Green2x. Straw-to-biogas pilot development and validation ahead of potential commercial deployment.

More than DKK100 million — Equinor, EIFO and other investors

Equity financing. This supports the Møn pilot; it does not establish financial close for the proposed full-scale Vordingborg facility. Valuation and individual investor terms undisclosed.[18]

Sindal Biogas expansion

Signed 4 August 2026

Sindal Biogas A/S; CIP Advanced Bioenergy Fund I, KK Invest and DBC Invest. Expansion from approximately 22 million to 44 million Nm³ biomethane annually.

DKK182 million / €24.5 million — NIB

13-year loan. Potential later carbon capture is identified, but should not be treated as commissioned infrastructure.[19]

Vegger acquisition and modernisation

19 October 2026

Fremsyn, borrowing through Biogem A/S. Integrated plant conversion described in section 01.

€6 million — Nefco

Group-channelled loan alongside other financiers; detailed terms undisclosed.[1]

The grant register identifies the supported project separately from the recipient’s wider investment programme. Green2x appears in both registers because its Møn pilot has equity financing and a distinct EUDP grant. RECLAIM shows a different sequencing issue: its €40 million grant is confirmed, but financial close is targeted for March 2028. The award secures a grant contribution while the project’s remaining financing must still reach closure.

Grant Remaining eligible cost
{{ g.name }}
{{ g.provider }}
{{ g.value }}

{{ g4Note }}

PROJECT AND AWARD TIMING SPONSOR / LEAD RECIPIENT FUNDED ACTIVITY GRANT, PROVIDER AND STRUCTURE

BOOST

Announced 17 December 2024

University of Copenhagen with BioCirc

Spectroscopic monitoring of feedstocks, digestion and digestate to improve biogas yield and nutrient management.

DKK4.30 million — GUDP; registered budget DKK4.78 million; project 2025–28. The register differs from the original anticipated DKK5.56 million award; the registered amount is used here.[20]

E-CH4 Booster

Announced April 2025; formal award August 2025

Pura Futura, with Aarhus University, EMS and education partners

Demonstration and industrialisation of biological methanation using biogenic CO₂ and hydrogen, including dynamic operation and operator training.

DKK24.66 million — Danish JTF; eligible costs DKK35.21 million. Demonstration grant; current registered project period runs from July 2025 to February 2028.[21]

PytoX — Advanced Pyrolysis Products

Announced April 2025

Energy Cluster Denmark consortium; Stiesdal SkyClean and Biogasclean technology

Biological conversion of dry pyrolysis gas into biomethane, alongside development of bio-oil and biochar products.

DKK12.58 million — Danish JTF; eligible costs DKK19.99 million; August 2025–January 2028. Technology development and testing, rather than confirmed commercial plant construction.[22]

BP2X

EUDP round II, December 2025

European Energy, Aarhus University, RENEW Energy and Danish Technological Institute

Scale-up of straw-based biogas at AU Foulum and design of integration with renewable methanol production.

DKK26.51 million — EUDP; budget DKK43.79 million; project 2026–28. Development and demonstration grant.[23]

RECLAIM, Vesthimmerland

Selected in 2025; grant confirmed in 2026

BioCirc Group and Vesthimmerland project companies

Conversion of an existing biogas plant into an integrated biomethane, renewable methanol and digestate-fertiliser facility.

€40 million — EU Innovation Fund. Grant agreement; target financial close March 2028, operation June 2030. A grant commitment does not establish that construction finance is already closed.[24]

Green2x Pilot Plant Møn

EUDP round I, 2026

Green2x, Bollfilter Nordic, Rambøll, DTU and Aarhus University

Validation and optimisation of straw conversion into biomethane and biogenic CO₂.

DKK23.9 million — EUDP. Separate development grant alongside the equity financing in section 03. Total grant-project budget was not disclosed in the located announcement.[25]

These awards extend financing to specific functions around digestion and upgrading. Ribe and Blåbjerg target CO₂ handling; Thorsø targets digestate pyrolysis and heat integration; Opti-BioN targets fertiliser production and emissions from digestate.

The awards also demonstrate the difference between a programme ceiling and actual project coverage. Ribe’s DKK10.27 million grant represents approximately 11.5% of its DKK88.96 million eligible costs, despite the JTF call’s headline support ceiling of up to 80%.

Grant Remaining eligible cost JTF headline ceiling, 80%
{{ g.name }}
{{ g.provider }}
{{ g.value }}

≤ Blåbjerg: announced partial allocation of up to DKK26.7 million against an application budget of DKK89.14 million.

PROJECT AND AWARD TIMING SPONSOR / LEAD RECIPIENT FUNDED ACTIVITY GRANT, PROVIDER AND STRUCTURE

PytoCCUS, Agri Energy Vrå

Announced April 2025

Energy Cluster Denmark consortium; host Agri Energy Vrå

Integration of pyrolysis, heat recovery and CO₂ capture/liquefaction, initially using the biogas-upgrading stream.

DKK27.24 million — Danish JTF; eligible costs DKK49.87 million; 2025–28. One integrated development award.[26]

PytoN, Vrå

Announced April 2025

Energy Cluster Denmark and the Stiesdal SkyClean ecosystem

Further development of the existing full-scale pyrolysis installation, component performance, heat integration and operational skills.

DKK26.69 million — Danish JTF; eligible costs DKK42.46 million; 2025–28. Technology improvement associated with the biogas/digestate system.[27]

Vacuum steam stripping and ammonia recovery

2025 award record

Cambi Danmark, BIOFOS and University of Southern Denmark

Recover ammonia and dissolved methane from digested sewage sludge, reducing methane release during dewatering.

DKK6.82 million — MUDP; budget DKK15.81 million; 2025–27. Flagship demonstration grant; exact award day not published in the record.[28]

Opti-BioN

Announced 9 December 2025

Innovation Centre for Organic Farming, Advanced Substrate Technologies, Aarhus University and Knud Jepsen

Convert digestate into liquid nitrate fertiliser through biological treatment, addressing methane and nitrogen losses.

DKK14.27 million — GUDP; budget DKK19.14 million; 2026–29. Development grant; organic approval remains a project objective.[29]

Thorsø fluidised-bed pyrolysis demonstration

December 2025

Dall Energy, Renegas and DTU

A 10 MW demonstration unit converting digestate fibres into biochar and useful heat, integrated with drying and biogas upgrading.

DKK49.98 million — EUDP; budget DKK98.64 million; 2026–29. Demonstration construction and integration grant.[30]

Ribe Biogas CO₂ capture and liquefaction

Announced 30 January 2026

Ribe Biogas A/S

On-site CO₂ capture, purification, liquefaction, tanks and commissioning, enabling subsequent permanent storage.

DKK10.27 million — Danish JTF; eligible costs DKK88.96 million; project ends December 2027. Investment grant for the defined on-site project.[31]

Blåbjerg CCS

Announced 30 January 2026

BioCirc / Blåbjerg Biogas

CO₂ capture, purification, liquefaction and associated civil works; approximately 11,000 tonnes/year intended removals.

Up to DKK26.7 million — Danish JTF, against an application budget of DKK89.14 million. Announced partial allocation; final legal review was required, and a later definitive individual award record was not identified.[32]

Nybro Pyrolyse

Announced 30 January 2026

Energy Cluster Denmark

Demonstration of electrified pyrolysis integrated with biogas, CO₂ capture and Power-to-X, including feedstock and heat integration.

DKK18.71 million — Danish JTF; eligible costs DKK28.97 million; project ends November 2028. Current register amount supersedes the initial DKK19.60 million announcement.[33]

BioKon

Announced 30 January 2026

Fonden Plast Center Danmark and industrial/research partners

Pretreatment, biological drying and thermochemical conversion of residues from agriculture, biogas and wastewater.

DKK23.04 million — Danish JTF; eligible costs DKK29.92 million; project ends December 2028. Research and demonstration grant.[34]

PyroSyd

Announced 30 January 2026

Danish Technological Institute

Digestate and sewage-sludge testing, resource mapping and business planning for potential pyrolysis facilities in Tønder and Aabenraa.

DKK8.04 million — Danish JTF; eligible costs DKK10.06 million; project ends February 2028. Feasibility and development funding; construction of the proposed plants is not financed by this award.[35]

The remaining awards support earlier-stage technology or downstream uses of biogas. Prometheus investigates methods to increase methane recovery, while SPRING and Reformable develop conversion routes to protein, fuels and chemical intermediates. These commitments finance research and technology development; they do not establish additional commercial gas-production capacity.

PROJECT SPONSOR / FUNDED ACTIVITY FUNDING AND TERMS

Prometheus — Microbial Electrochemical Methanation Initiative

Announced 16 April 2026

University of Southern Denmark-led international consortium. Electrode-linked microorganisms to improve conversion of organic waste into biomethane.

Almost DKK50 million — Novo Nordisk Foundation. Research grant to the consortium; no commercial plant construction commitment or Danish-only allocation established.[36]

SPRING

Announced December 2025

DTU-led consortium. Conversion of food-sector side streams through biogas into microbial protein.

DKK9.57 million — GUDP; budget DKK14.16 million; 2026–30. Downstream biosolutions development.[37]

Reformable — Fuels and Chemicals from Biogas

2025 Innoexplorer award

DTU. Maturation of technology for converting biogas into fuel and chemical intermediates.

DKK1.5 million — Innovation Fund Denmark, matching the recorded project budget; 2025–26. Research-commercialisation grant.[38]

Reformable — VILLUM P2X Accelerator

Announced December 2024

DTU/Reformable. Catalyst and process development for reacting CO₂ with methane.

DKK4.6 million reported by the recipient; the accompanying accelerator communication states DKK4 million over two years. A separate foundation-backed award, but the public amount discrepancy remains unresolved.[39]