UK GGSS extension: more time to deliver biomethane projects, a shorter tariff life for late starters

The Green Gas Support Scheme’s commissioning extension gives eligible biomethane projects until 31 March 2030 to complete construction, begin grid injection and submit their registration applications. The change took effect on 16 October 2026, with final Ofgem guidance published that day. It applies across England, Scotland and Wales.[1]

The commercial benefit is substantial for projects that would otherwise miss the previous deadline. However, access depends on the application’s date, its individual tariff-guarantee conditions and available scheme budget. Later commissioning also reduces the remaining support period.

GGSS supports eligible biomethane produced through anaerobic digestion and injected into the gas grid. The extension separates the deadline for entering the application process from the deadline for completing a project.

MilestonePosition following the amendment
New stage-one applicationsMust still be submitted by 31 March 2028
Commissioning, first injection and stage-three applicationOuter deadline extended to 31 March 2030 for eligible applicants
Maximum support durationRemains 15 years
Final supported periodCannot extend beyond 31 March 2043
Territorial coverageGreat Britain; Northern Ireland is outside the scheme

The additional two years therefore provide a delivery window for qualifying applications, while retaining the existing entry cutoff and final payment boundary.[1]

DESNZ explicitly links the 2043 limit to avoiding an extension of costs beyond the existing lifetime of the Green Gas Levy, which funds GGSS. The policy accommodates slower project delivery while containing the duration of levy-funded commitments.[2]

The amendment does not move every existing project’s deadline. Different application cohorts retain different statutory limits.

Outer commissioning and registration deadline, by the date the stage-one tariff-guarantee application was properly made.

Application window Outer deadline Extended deadline Only with Ofgem-approved revision Not revived
10 DEC 2025 · REISSUE ELIGIBLE 16 OCT 2026 · IN FORCE
Before 4 Jun 2024 30 November 2025; the new amendment does not revive that deadline
4 Jun 2024 – 9 Dec 2025 31 March 2028
10 Dec 2025 – 15 Oct 2026 31 March 2028, unless Ofgem approves a revision allowing a later deadline
16 Oct 2026 – 31 Mar 2028 31 March 2030, subject to the project’s individual deadline
2024 2025 2026 2027 2028 2029 2030 2031

The amendment permits Ofgem to reissue tariff-guarantee notices for applications made on or after 10 December 2025, substituting a later date and, where necessary, changing or adding conditions.[3]

For applicants from before that eligibility date, DESNZ identifies withdrawal and reapplication as a possible route if the original commissioning date becomes unachievable. Re-entry remains subject to the prevailing eligibility conditions and available budget.[4]

Withdrawal should therefore be assessed as a fresh application decision with funding risk.

The three-stage application structure remains important:[5]

The project must be sufficiently developed to provide connection-agreement evidence, planning-permission details, capacity and expected injection volumes. Evidence that construction and commissioning funds are available and formally committed must be submitted within three weeks of the provisional tariff-guarantee notice. The plant must be commissioned, injection must have begun, and the registration application must be complete.

The effective project deadline

EFFECTIVE DEADLINE = EARLIER OF (expected commissioning date + 182-day grace period) or (applicable statutory cutoff)

The injection deadline stated in a tariff-guarantee notice already incorporates the available grace period. Applicants should not add another 182 days to it, and no grace period extends beyond the applicable final cutoff.[6]

For example, a project with an expected commissioning date in early 2027 could still lose its tariff guarantee during 2027 if it misses its individual deadline and has not secured an eligible revision. The national March 2030 date does not itself protect that project.

Existing applicants must request and substantiate a revised date

The authorised signatory must email GGSS.app@ofgem.gov.uk, providing the application reference and proposed new expected injection date. Ofgem checks the revised timetable against the application evidence, may request updated documents and, where a guarantee has already been granted, reissues the notice if it accepts the change.

Eligible applications in the budget queue can also request a revised date without losing their original application date or queue position. Once injection has begun, however, the expected commissioning date cannot be moved beyond the actual first-injection date.[7]

Choosing the latest possible date can postpone revenue

Ofgem’s guidance states that payments cannot begin before the approved expected commissioning date, including an amended date. Consequently, requesting March 2030 merely to maximise schedule protection could leave earlier production without GGSS payments if the plant finishes sooner.[6]

The practical objective is a credible revised date supported by the construction and connection programme. The date affects both delivery flexibility and when supported revenue can begin.

The statutory tariff start date is linked to registration: the date on which the stage-three application is considered properly made. First injection alone does not establish that date. An incomplete registration submission can therefore have a direct revenue consequence.[8]

31 MAR 2043 · FINAL CUTOFF
Start 31 Mar 2028 15YRS
Start 31 Mar 2029 14YRS
Start 31 Mar 2030 13YRS
2028 2030 2034 2038 2042 2044
Supported period Support lost to later start

Assumes commissioning, properly made registration and the approved expected commissioning date coincide.

These durations follow from the unchanged maximum term and fixed 2043 cutoff.[2]

05 — Implications for biomethane

Project preservation, financing pressure and a binding budget queue

The greatest benefit accrues to viable projects facing delivery delays

For an otherwise eligible project unable to complete by March 2028, the relevant comparison may be:

a shorter supported operating period versus losing GGSS access altogether.

Retaining that revenue stream can justify continued development where planning, construction or grid-connection delays would previously have made the schedule untenable.

This is the principal deployment benefit: more qualifying projects may reach operation. It does not establish how much additional capacity will be delivered or when. DESNZ has not produced a new full impact assessment quantifying deployment attributable specifically to this amendment.[2]